Rinnai Australia 13 Operation / Installation Manual
Join inlet of primary pump to tee at cold inlet fitting on tank with 32mm pipe.
Join outlet of primary pump to inlet of cold (bottom) pipe on manifold.
Fit cover so that pump is weatherproof. Ensure power cable enters pump from below and that it
is not a track for water to enter pump.
Remaining port on the tee is the cold water inlet to the system. It is also the ringmain return
point.
Extend 32 mm hot return pipe (centre pipe) from end of manifold to the return fitting on the tank
with union as required. This fitting is 385 mm from the tank base.
System is now ready to be plumbed to the building.
Plug primary pump(s) into the thermostatic controller mounted on the tank.
Plug power supply to the thermostatic controller into an available GPO. DO NOT turn ‘ON’.
Plug water heaters on DD2 - DD6 to an available GPO (one per heater is required). DO NOT
turn ‘ON’.
When direct flueing through the wall that the water heaters are mounted on, it
may be necessary to attach flue to water heater and push it through the wall
before attaching the water heater to the wall.
Primary pump and/or primary pipe work may need to be increased for long runs of
primary pipe work, or installation with many bends in the pipe work between tank
and manifold.
DD1 Models, Drawing and Specifications
All Dimensions are (mm)
DD Model PTR
Inclusions
Primary
pump
MJ Rating
(HD Water
Heater)
Total
System
Weight
(kG)
Fittings
Hot Cold PTR Gas
*DD1 200e/
250 ext
1 * HT 575
(46 kW)
UPS20 -
60B
199 110
RP1 1/4”
(32mm)
*RP1 1/4”
(32mm)
RP 3/4”
(20mm)
RP 3/4”
(20mm)
DD1C 211e
250 ext
1 * HT 575
(46 kW)
UPS25 -
80B
211 125
RP1 1/4”
(32mm)
*RP1 1/4”
(32mm)
RP 3/4”
(20mm)
RP 3/4”
(20mm)
DD1 200e/
315 ext
1 * HT 575
(46 kW)
UPS20 -
60B
199
120
RP1 1/4”
(32mm)
RP1 1/4”
(32mm)
RP 3/4”
(20mm)
RP 3/4”
(20mm)
*DD1 200i/
250 int
1 * HT 575
(46 kW)
UPS20 -
60B
199
110
RP1 1/4”
(32mm)
*RP1 1/4”
(32mm)
RP 3/4”
(20mm)
RP 3/4”
(20mm)
DD1C 211e
315 ext
1 * HT 575
(46 kW)
UPS25 -
80B
211 125
RP1 1/4”
(32mm)
*RP1 1/4”
(32mm)
RP 3/4”
(20mm)
RP 3/4”
(20mm)
DD1 200i/
315 int
1 * HT 575
(46 kW)
UPS20 -
60B
199
120
RP1 1/4”
(32mm)
RP1 1/4”
(32mm)
RP 3/4”
(20mm)
RP 3/4”
(20mm)
DD1C 211i
250 int
1 * HT 575
(46 kW)
UPS25 -
80B
211 125
RP1 1/4”
(32mm)
*RP1 1/4”
(32mm)
RP 3/4”
(20mm)
RP 3/4”
(20mm)
*DD1 250e/
250 ext
2 * HT 575
(92 kW)
UPS20 -
60B
250 120
RP1 1/4”
(32mm)
*RP1 1/4”
(32mm)
RP 3/4”
(20mm)
RP 3/4”
(20mm)
DD1C 211i/
250 int
1 * HT 575
(46 kW)
UPS25 -
80B
211 125
RP1 1/4”
(32mm)
*RP1 1/4”
(32mm)
RP 3/4”
(20mm)
RP 3/4”
(20mm)
DD1 250e/
315 ext
2 * HT 575
(92 kW)
UPS20 -
60B
250 130
RP1 1/4”
(32mm)
RP1 1/4”
(32mm)
RP 3/4”
(20mm)
RP 3/4”
(20mm)
*DD 250
1 * HT 575
(46 kW)
N/A N/A 73
RP1 1/4”
(32mm)
*RP1 1/4”
(32mm)
RP 3/4”
(20mm)
RP 3/4”
(20mm)
DD 315
1 * HT 575
(46 kW)
N/A N/A
88
RP1 1/4”
(32mm)
RP1 1/4”
(32mm)
RP 3/4”
(20mm)
RP 3/4”
(20mm)
DD COMBO
250
1 * HT 575
(46 kW)
N/A N/A
75
RP1 1/4”
(32mm)
RP1 1/4”
(32mm)
RP 3/4”
(20mm)
RP 3/4”
(20mm)
DD COMBO
315
1 * HT 575
(46 kW)
N/A N/A
90
RP1 1/4”
(32mm)
RP1 1/4”
(32mm)
RP 3/4”
(20mm)
RP 3/4”
(20mm)
DD1 250L only tank supplied with 32 mm brass plug to plug one of the unused cold
inlet ports.
NOTE
NOTE
NOTE
GENERAL INSTALLATION INSTRUCTIONS